Construction project cost control tracker

Ingests project budget, committed costs, and actuals to calculate earned value metrics, flag cost and schedule variances by cost code, forecast final cost at completion, and produce a cost control narrative for monthly…

download .md

Purpose

Turn raw budget, commitment, and actual cost data into a structured earned value analysis that pinpoints where a project is over or under, forecasts the final cost at completion, and produces a defensible cost control narrative for monthly project reviews. Eliminates the manual reconciliation between the budget, the commitment ledger, and the accruals — and replaces vague "we're a little over" reporting with quantified variance by cost code.

When to Use

Invoke this skill when the user asks to:

  • Track spend against budget on a construction or capital project
  • Run earned value analysis (CPI, SPI, EAC, ETC) on a project
  • Diagnose why a project is trending over budget and by how much
  • Prepare a monthly cost control report or variance narrative
  • Identify which cost codes are driving an overrun before month-end close
  • Forecast the estimated cost at completion for a project or work package

Inputs Required

Before starting, collect:

  • Cost breakdown structure: Cost codes / WBS elements with descriptions (e.g., 03300 Concrete, 05100 Structural Steel)
  • Original and revised budget: Budget at Completion (BAC) per cost code, plus approved change orders
  • Committed costs: Purchase orders and subcontracts issued to date, per cost code
  • Actual costs incurred: Invoiced/paid amounts plus accruals to date (Actual Cost, AC), per cost code
  • Percent complete: Physical or quantity-based % complete per cost code (used to calculate Earned Value)
  • Data date: The as-of date for all actuals and progress
  • Schedule status (optional): Planned % complete or Planned Value per cost code, for schedule variance

If percent complete is only available at project level, note that cost-code-level Earned Value is estimated and flag which codes need field verification. If Planned Value is missing, deliver cost variance only and mark schedule metrics as unavailable.

Instructions

Step 1: Reconcile the Cost Ledger

Before any analysis, validate the data set:

  • Confirm Budget = Original Budget + Approved Change Orders for each cost code; flag any code where the revised budget doesn't reconcile
  • Confirm Committed ≥ Actual for each code — if actuals exceed commitments, flag as uncommitted spend (a control gap)
  • Identify any cost code with actuals but zero budget (unbudgeted scope) and any code with budget but no commitment or activity
  • Total the columns and confirm project-level BAC, committed, and AC sum correctly

Step 2: Calculate Earned Value Metrics

For each cost code and at the project roll-up, compute the core EVM values:

  • BAC (Budget at Completion) = revised budget for the code
  • EV (Earned Value) = % Complete × BAC — the budgeted value of work actually done
  • AC (Actual Cost) = actuals incurred + accruals to date
  • PV (Planned Value) = planned % complete × BAC (if schedule data provided)

Then derive:

  • CV (Cost Variance) = EV − AC. Positive = under budget; negative = over budget
  • CPI (Cost Performance Index) = EV / AC. Below 1.0 = spending more than the work is worth
  • SV (Schedule Variance) = EV − PV (if PV available). Negative = behind schedule
  • SPI (Schedule Performance Index) = EV / PV (if PV available)

Step 3: Forecast Cost at Completion

Produce forecasts using the appropriate EAC method and explain the assumption:

  • EAC (CPI-based) = BAC / CPI — assumes current cost performance continues (the default for most industrial projects)
  • EAC (bottom-up) = AC + Estimate to Complete, where ETC = remaining budget adjusted by any known changes — use when the team has a fresh forecast for remaining work
  • VAC (Variance at Completion) = BAC − EAC — the projected over/under at the end
  • TCPI (To-Complete Performance Index) = (BAC − EV) / (BAC − EAC) — the cost efficiency required on remaining work to hit budget; flag as unrealistic if above 1.10

Present both a CPI-based and a bottom-up EAC at project level so the reader sees the range.

Step 4: Flag and Rank Variances

Classify every cost code by variance severity:

  • Critical — CPI < 0.90 or CV exceeding 5% of the code's BAC: driving the overrun, needs immediate action
  • Watch — CPI 0.90–0.98: trending unfavorable, monitor closely
  • On track — CPI 0.98–1.05
  • Favorable — CPI > 1.05: under-running, check for missed accruals or under-reported progress before celebrating

Rank the Critical and Watch codes by absolute dollar impact on VAC — the biggest dollar drivers first, not the worst percentages.

Step 5: Write the Cost Control Narrative

Produce a plain-language narrative a project sponsor can read without decoding acronyms:

  • Headline: Overall project status — CPI, SPI (if available), and forecast VAC in one sentence
  • What's driving it: The top 3 cost codes moving the forecast, with the dollar variance and the likely field/commercial cause (scope growth, productivity, escalation, quantity overrun, rate variance)
  • Recovery actions: Specific corrective actions per critical code (re-sequence, renegotiate, value-engineer, submit change order, tighten field controls)
  • Risks and watch items: Codes trending unfavorable and any data quality flags from Step 1

Output Format

  • Structure: EVM data table by cost code → project roll-up summary → variance ranking → written cost control narrative
  • Length: 800–1,200 words plus the tables
  • Format: Structured tables for the metrics; prose for the narrative section
  • Sections: Data reconciliation flags → EVM metrics table (cost code level) → Project roll-up (CPI, SPI, EAC range, VAC, TCPI) → Ranked variance list (Critical/Watch) → Cost control narrative
  • Tone: Project controls specialist — quantified, neutral, and action-oriented. State variances as facts with dollar figures; no hedging, no filler.

Quality Checklist

Before delivering output, verify:

  • [ ] Every cost code has EV, AC, CV, and CPI calculated (no blanks unless data was missing)
  • [ ] Revised budget reconciles to original budget plus change orders for each code
  • [ ] Both a CPI-based and bottom-up project EAC are shown, with the assumption stated
  • [ ] Variance ranking is ordered by absolute dollar impact on VAC — not by percentage
  • [ ] The narrative names the top 3 dollar drivers with specific likely causes, not generic statements
  • [ ] Any data quality flags (uncommitted spend, unbudgeted scope, project-level-only % complete) are surfaced explicitly

Notes

  • The single most common data error is stale or optimistic percent complete inflating Earned Value — when CPI looks suspiciously favorable, challenge the progress before the actuals.
  • CPI-based EAC is the conservative default for industrial capital work because cost performance rarely improves late in a project; use bottom-up only when the field team has genuinely re-estimated remaining work.
  • A TCPI above 1.10 means the team must run remaining work more efficiently than it has managed to date — treat it as a signal the budget is likely lost, not a target.
  • Favorable variances early in a project are often missing accruals rather than real savings; verify before reporting them as gains.

How to use this skill

This file is a Claude Code skill in Anthropic's standard format — markdown with YAML frontmatter at the top.

Installing in Claude Code:

  • ~/.claude/skills/<folder-name>/SKILL.md — auto-loads in every session anywhere on your machine (recommended for skills you'll use across multiple projects)
  • <your-project>/.claude/skills/<folder-name>/SKILL.md — auto-loads only when working in that project (recommended for project-specific skills)

Restart Claude Code or open a new session to register.

Using in Claude.ai, ChatGPT, Gemini, or other AI tools:

  1. Drag this file into a new chat, or copy and paste its contents